An error has occurred. An error has occurred.
An error has occurred. An error has occurred.

F-35 Bauer-Hockley Stormwater Detention Basin

F-35 Bauer-Hockley Stormwater Detention Basin
An error has occurred. Error: Side Menu is currently unavailable.

Recent Actions

October 12, 2021  - Harris County Commissioners Court approved a development agreement with Harris County Municipal Utility District No. 565 in support of this project.

January 5, 2021 - Harris County Commissioners Court authorized an amendment in the amount of $1,000 for construction of this project.

December 15, 2020 - Harris County Commissioners Court acknowledged substantial completion of the construction of the stormwater detention basin and Phase 1 improvements, and moved identified expenses to the fixed asset module where appropriate.

May 19, 2020 - Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update changes funding to reflect engineers estimate and pending construction bid. Additionally, $79,840 was added to the contract agreement for this project.

March 24, 2020 – Harris County Commissioners Court approved an additional $659,234 for Phase 1 construction of this basin.

December 17, 2019 – Harris County Commissioners Court approved an additional $8,625 for Phase 1 construction of this basin.

May 14, 2019 – Harris County Commissioners Court awarded a $4.19 million contract for construction of this project.

March 26, 2019 – Harris County Commissioners Court approved a $79,435 contract with an engineering firm for materials engineering and testing services in support of this project. 

December 18, 2018 – Harris County Commissioners Court accepted a Preliminary Engineering Report and authorized the Flood Control District to proceed with design and construction of this project. 

November 13, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct materials engineering and testing services in support of this project.

Project Description

This project is part of the Little Cypress Creek Frontier Program, which focuses on the 52 square-mile Little Cypress Creek watershed in northwest Harris County. This area, which is experiencing rapid development with construction of the Grand Parkway, lacks sufficient natural drainage to accommodate expected growth. By collaborating with landowners and developers, the program works to identify a large-scale, mutually beneficial plan for drainage that cost effectively maximizes stormwater mitigation, flood damage reduction and water quality, as well as opportunities for public recreational amenities and open space.

The Bauer-Hockley basin project involves design and construction of a stormwater detention basin to reduce flooding risks in the Little Cypress Creek Watershed. This basin will help reduce existing flood levels and allow for future stormwater infrastructure improvements that will reduce the risk of flooding in this area. The 101-acre basin site is located north of the intersection of Bauer-Hockley and Becker roads in northwest Harris County.

Construction on Phase I of the ultimate basin began in August 2019 and was completed in Fall 2020. During this phase, crews excavated approximately 383 acre-feet of detention, which will hold approximately 124.8 million gallons of stormwater.

Starting January 2021, excavation of the property will continue under an excavation and removal (E&R) contract. The E&R contractor removes a set amount of soil, which helps expedite the construction of the detention basin and keep costs down. This E&R contract allows the contactor to excavate no more than 500,000 cubic-yards of soil.

By allowing a willing E&R contractor to appropriately use material excavated at the site, implementation of an E&R project helps reduce future construction costs, as compared with typical excavation and disposal costs.

When all planned phases are complete, the basin is expected to hold a total of approximately 251 million gallons, or more than 770 acre-feet, of excess stormwater.

Projects that are part of the Little Cypress Creek Frontier Program will be partially funded by the 2018 Bond Program. Development impact fees also support the frontier program. Bond Project F-35 is a “Local Only” bond project, which means there is no other funding partner at this time and construction costs will be paid with bond funding.

Total allocation for this project is currently $5.3 million on the Bond Project List.

Stormwater detention basins reduce flooding risks and damages during heavy rain events by safely storing excess stormwater and slowly releasing it back to the bayou when the threat of flooding has passed.

Community Engagement Meeting

A community engagement meeting was held on Wednesday, November 14, 2018.