May 24, 2022 – Harris County Commissioners Court approved a Joint Funding Structure between Harris County and the Harris County Water Control and Improvement District Number 50 (WCID 50). in support of this project.
May 10, 2022 - Harris County Commissioners Court approved a change in contract with a construction contractor resulting in an addition of 5 calendar days and $56,669.50 to the contract amount in support of this project.
May 10, 2022 - Harris County Commissioners Court approved an amendment to an agreement with an engineering firm in the amount of $27,296.00 in support of this project.
October 26, 2021 - Harris County Commissioners Court approved an engineering report in support of this project.
September 28, 2021 – Harris County Commissioners Court authorized a purchase order for construction materials testing and inspection services in support of this project.
September 28, 2021 – Harris County Commissioners Court authorized an agreement for engineering services in the amount of $157,446 in support of this project.
June 30, 2020 - Harris County Commissioners Court authorized the Flood Control District to negotiate agreements with Harris County Water Control and Improvement District No. 50, with each partner contributing $4.75 million. The project will reduce structural flooding in the watershed.