May 19, 2020 – Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update changes funding estimate to reflect actual expenditures.
November 12, 2019 – Harris County Commissioners Court authorized negotiations with various political jurisdictions for agreements in support of collaborative efforts to implement the Clear Creek Federal Flood Risk Management Project and Clear Creek watershed bond projects.
March 2019Harris County Flood Control District sent partnership funding to the City of Nassau Bay.
January 29, 2019 – Harris County Commissioners Court approved a $125,000 interlocal agreement with the City of Nassau Bay in support of this project.
December 18, 2018 – Harris County Commissioners Court authorized negotiations with the City of Nassau Bay in support of this project.
October 23, 2018 – Harris County Commissioners Court authorized and initiated this project.