An error has occurred. An error has occurred.
An error has occurred. An error has occurred.

C-32 Cutten Stormwater Detention Basin Improvements

C-32 Cutten Stormwater Detention Basin Improvements
An error has occurred. Error: DDR Menu is currently unavailable.

Recent Action

December 13, 2022 - Harris County Commissioners Court approved a change in the construction contract adding 36 calendar days and an additional $39,804 to the contract amount.

August 2, 2022 – Harris County Commissioners Court authorized a change in contract, adding 30 calendar days and resulting in the addition of $11,759 to the contract amount, in support of this project.

May 24, 2022 – Harris County Commissioners Court approved a change in contract adding 86 calendar days and $18,456 to the construction contract amount.

July 14, 2020 – Harris County Commissioners Court authorized the purchase of $29,400 in wetlands mitigation credits from the Greens Bayou Wetlands Mitigation Bank in support of this project.

June 9, 2020 – Harris County Commissioners Court approved a $166,000 agreement with an engineering firm for materials engineering and testing services in support of this project.

June 6, 2020 – Harris County Commissioners Court approved a $166,000 agreement for materials engineering and testing services in support of this project.

May 19, 2020 – Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Updates corrects project title to include "stormwater detention" and “improvements”; funding updated to reflect engineers estimate and pending construction bid; and partner funding amount was removed as none was secured.

April 28, 2020 – Harris County Commissioners Court awarded a $14.2 million contract for construction of this project.

March 24, 2020 – Harris County Commissioners Court authorized negotiations for materials engineering and testing services in support of this project.

March 10, 2020 – Harris County Commissioners Court authorized an additional $129,592 for engineering services in support of this project.

December 17, 2019 – Harris County Commissioners Court authorized the purchase of wetland mitigation credits from the Greens Bayou Wetlands Mitigation Bank in support of this project.

November 12, 2019 – Harris County Commissioners Court accepted a preliminary engineering report and authorized the design and construction of this project.

November 13, 2018 – Harris County Commissioners Court approved a $739,525 agreement with an engineering firm for final design of this project.

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for final design of this project.

Project Description

Bond Project C-32 will construct a series of stormwater detention basin in upper Greens Bayou. The Flood Control District is currently excavating the fifth compartment of the Cutten Stormwater Detention Basin, which spans 235 acres near Cutten Road and State Highway 249. The first four compartments are located across from the expansion property, south of Greens Bayou. Once the expansion of the stormwater is complete, the capacity of the stormwater detention basin will double from holding almost 221 million gallons (compartments 1-4), to almost 503 million gallons total. Compartment five, under construction, is expected to hold 282 million gallons of stormwater.

Location

The original footprint of the stormwater detention basin is located south of Greens Bayou and the fifth compartment is located north of Greens Bayou, near Cutten Road and State Highway 249.

Stage

This project is in the CONSTRUCTION stage and is expected to be complete in summer 2022.

Bond Project Listing

Total allocation for all future stages and phases of Bond Project C-32 on the Bond Project List is currently $15.1 million.

Project Photos

C-32: Active construction in Cutten Stormwater Detention Basin