An error has occurred. An error has occurred.
An error has occurred. An error has occurred.

F-122 Watershed Wide Project Implementation Program

F-122 Watershed Wide Project Implementation Program
An error has occurred. Error: DDR Menu is currently unavailable.

Recent Actions

May 19, 2020 – Harris County Commissioners Court approved new Bond ID added to the 2018 Bond Program List.

February 25, 2020 – Harris County Commissioners Court approved a $47.6 million agreement with an engineering firm to manage an implementation plan for bond projects within the Halls Bayou watershed.

November 12, 2019 – Harris County Commissioners Court approved an additional $40,000 for engineering services in support of this project.

June 25, 2019 – Harris County Commissioners Court authorized a $400,000 agreement with an engineering firm to research and develop an implementation plan for Halls Bayou watershed bond projects.

May 14, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm to assist with a watershed-wide implementation program for Halls Bayou projects.

Project Description

Bond Project F-122 is the bond implementation manager for the bond projects included within the 2018 Bond Program.

The Flood Control District is taking a watershed-wide approach to planning for this area. This approach provides a holistic view of activity in the watershed and enables the Flood Control District to deliver projects strategically and efficiently in a heavily developed area. Projects may include construction of stormwater detention basins, channel improvements on Halls Bayou tributaries, and right of way acquisition for floodplain preservation.

Background

The projects identified in the 2018 Bond Program were originally identified in the 2013 Halls Ahead Study Vision Plan, which was developed with extensive community input between 2012 and 2013. The Vision Plan outlines an ambitious $1.75 billion plan for more than 20 miles of channel conveyance improvements and construction of stormwater detention basins to hold more than 10,000 acre-feet, or approximately 32.6 billion gallons, of stormwater.

In 2019, the Flood Control District completed an update of the 2013 Vision Plan and developed the Halls Bayou Phasing Study. The updated Vision Plan incorporated substantial updates enhanced modeling techniques, improved data collection (such as structure inventory, unit cost estimates, updated existing rights-of-way, flood claim data and other items), and insights gathered from ongoing stakeholder coordination.

The Phasing Study formulates a navigable pathway towards realizing the Vision Plan with smaller and more manageable project pieces. The phased approach for the Vision Plan will facilitate annual budget planning and securing of funds, early identification of potential funding partnerships, and will allow time for right-of-way acquisition.

The Phasing Study breaks the 58 flood risk reduction projects identified in the Vision Plan into 12 phases, with estimated costs between $100 million and $150 million per phase. Each project included in the recommended phases is designed to improve the level of protection from riverine flooding for structures, while also providing environmental benefits where possible. Each phase works together to provide benefits across Halls Bayou.

Projects may include channel conveyance improvements, construction of stormwater detention basins and bridge modifications. Channel conveyance improvement projects could include: widening and/or deepening of channels, construction of grass-lined sections, retaining walls, concrete lining, enclosure with box culverts, and natural stable channel design. Projects designs will consider aesthetics, the need for right-of-way acquisition, environmental enhancement, recreational opportunities and budgetary constraints.

Public Information Session

A series of projects in the Halls Bayou watershed are included in two separate applications for federal funding through the Community Development Block Grant for Mitigation (CDBG-MIT) Program. The projects included are Bond Project IDs: C-01, C-23, C-24, C-26, C-28, C-30 and C-41. A virtual Public Information Session to discuss these projects was held on:

Date: Wednesday, September 23, 2020
Time: 6:30 p.m. to 7:30 p.m.

The official public comment period for the CDBG-MIT applications will be open from October 3 – October 16, 2020. We encourage residents to learn more about the application process, submit a comment and view the meeting presentation and video:

Virtual Meeting

The Harris County Flood Control District held a virtual meeting for the Halls Bayou Bond Program – Summer 2022 Updates in the Halls Bayou watershed for the following Bond Project IDs: C-01, C-23, C-24, C-25, C-26, C-28, C-30, C-35, C-41, and CI-006.

The virtual meeting was held on:

Date: Thursday, June 30, 2022
Time: 6:30 p.m. to 7:30 p.m.

Virtual Meeting

The Harris County Flood Control District held a virtual meeting for the Halls Bayou Bond Program – Winter 2022 Updates in the Halls Bayou watershed for the following Bond Project IDs: C-01, C-23, C-24, C-25, C-26, C-28, C-30, C-35, C-41, and CI-006.

The virtual meeting was held on:

Date: Thursday, December 15, 2022
Time: 6:30 p.m. to 7:30 p.m