December 14, 2021 - The Flood Control District transmitted a preliminary engineering report dated October 2021 for this project.
July 20, 2021 - Harris County Commissioners Court authorized the Flood Control District to purchase a tract of land in support of this project.
January 5, 2021 - Harris County Commissioners Court authorized the acquisition of 19 tracts in support of this project.
May 19, 2020 – Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update changes funding to amount secured from NRCS Pilot Program.
October 8, 2019 – Harris County Commissioners Court authorized the Flood Control District to accept a $28 million U.S. Department of Agriculture grant for the Emergency Watershed Protection Pilot Program that includes funds for this and other projects
September 24, 2019 – Harris County Commissioners Court authorized and initiated this project