Z-02 Meyergrove Stormwater Detention Basin D500-11-00

Z-02 Meyergrove Stormwater Detention Basin D500-11-00
An error has occurred. Error: DDR Menu is currently unavailable.

Recent Actions

January 10, 2023 – Harris County Commissioners Court authorized the Flood Control District to accept a $5,77,899 grant from the Federal Emergency Management Agency, with a required match of $1,926,3000.

November 10, 2020 - Harris County Commissioners approved an additional $33,940 for design and construction stage engineering services in support of this project.

May 19, 2020 - Harris County Commissioners Court approved new Bond ID added to the 2018 Bond Program List.

January 28, 2020 - Harris County Commissioners Court approved a $154,193 agreement with an engineering firm for design and construction phase engineering services in support of this project.

December 17, 2019 - Harris County Commissioners Court authorized and initiated the planning, design and construction of the City of Houston partnership project for the Meyergrove Stormwater Detention Basin, and recommended that it be officially designated as D500-11-00 for identification purposes.

Project Description

This project is for the design and construction of the Meyergrove Stormwater Detention Basin (D500-11-00), which is located just inside Loop 610 between Brays Bayou and North Braeswood Boulevard, as well as a second, smaller basin (D500-12-00) in the median between North and South Braeswood and between the railroad crossing and Linkwood Drive.

Public Information Session

A virtual public meeting to learn more about this project was held on.

Date: Monday, October 12, 2020
Time: 6:30 p.m. to 7:30 p.m.

You can submit a comment and see the meeting presentation and video by clicking the links below.

Virtual Meeting Video Presentation Summary Submit a Comment